Quote
Samples
  •  FREE DELIVERY on all orders over £1000*

0 £0.00

Installing Stringer Steps

Cedar Classic Composite Decking In Hertfordshire - Assured Composite

Installing Stringer Steps

Stringer steps consist of a row of stringers attached to a raised area and a landing area to form a framework of steps.

How to prepare stringer steps

1. We recommend landing areas to be on a solid ground. If the ground is soft or uneven we recommend concreting posts into the ground to support each stringer (following the process on page 13)

2. Carefully plan the area taking into account the deck board and riser width when designing the tread and rise dimensions. Ensure the rise and tread is consistent along the steps and allow space at the bottom of the stringers for the thickness of the base plate

3. Measure and cut stringers and base plates where required

4. Measure and fix the stringer hangers to the raised area using coach screws, pre-drilling all holes. Reinforce the raised area if required and ensure each stringer is spaced at 300mm max intervals centre to centre

How to fix stringer base plates to a concrete base

1. Measure and fix the base plates to the landing area by pre-drilling holes and screwing them down using expansion screws. We advise every 100mm approx intervals.

2. Fix stringers to hangers by screwing together using coach screws, pre-drilling all holes.

3. Use “L” brackets to fix stringers to base plates using coach screws, pre-drilling all holes. Ensure that each stringer is spaced at 300mm max intervals centre to centre.

Need Some Help? We've Got You Covered!

Explore our frequently asked questions or use our convenient search feature to locate the information you need. Alternatively give our team a call on 01664 400 140 and we'd be happy to help!

© Assured Composite 2024. All Rights Reserved. Assured Composite is a registered company in England and Wales under Company Number: 10166812. VAT Number: 244830019.
Top